dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| ||||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | R3 juh | 1 892 m | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 5/2015 | 12/2023 | |||||
2 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 1 544 m | 77 mil. € | 2 | 2 | 2/2016 | 2/2025 | ||||||
3 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 2 956 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 2/2016 | 2/2025 | |||||
4 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 206 m | 59 mil. € | 12 862 | 3 | 4 | 9/2014 | 2/2025 | |||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 1 640 m | 143 mil. € | 12 157 | 3 | 4 | 9/2014 | 4/2025 | |||||
6 | 47. | 7/2029 | R2 | 14,0 km | 2 | R2 východ | 891 m | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 12/2014 | 7/2028 | |||||
6 úsekov |
42,5 km |
2 - 4 |
9 128 m |
665 mil. € |
5 550 - 12 862 | 2,8 |
3,2 |
12/2023 - 7/2028 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku