dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | R3 juh | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 12/2023 | ||||
2 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 2 | 2 | 2/2025 | |||||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 2/2025 | ||||
4 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 12 157 | 3 | 4 | 4/2025 | ||||
5 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | R1 BB - RK | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 6/2027 | ||||
6 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | R3 stred (Turiec) | 305 mil. € | 3 | 3 | 12/2033 | |||||
6 úsekov |
54,7 km |
2 - 4 |
1 579 mil. € |
5 550 - 13 204 | 2,5 |
2,8 |
12/2023 - 12/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku