dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
171,0 km |
2 - 4 |
2 336 mil. € |
3,8 |
3,5 |
|||||||||
1 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 692 - 940 | 2 | 2 | ||||
2 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 635 - 690 | 2 | 4 | ||||
3 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 177 - 189 | 4 | 3 | ||||
4 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 359 - 396 | 5 | 5 | ||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 454 - 531 | 5 | 4 | ||||
6 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 473 - 644 | 5 | 5 | ||||
7 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 384 - 424 | 4 | 3 | ||||
8 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 240 - 264 | 3 | 3 | ||||
9 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 205 - 412 | 4 | 3 | ||||
10 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 146 - 252 | 4 | 3 | ||||
11 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 911 - 1 315 | 3 | 3 | ||||
12 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 525 - 852 | 4 | 4 | ||||
171,0 km |
2 - 4 |
2 336 mil. € |
3,8 |
3,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku