dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | ||||||
2 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 1 988 - 4 251 | 4 | 3 | ||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 6 176 | 4 | 3 | ||||
4 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 6 810 - 9 018 | 2 | 4 | ||||
5 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 928 - 6 192 | 4 | 3 | ||||
6 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 2 053 - 2 240 | 3 | 3 | ||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 2 085 - 4 153 | 4 | 3 | ||||
77,0 km |
2 |
1 100 mil. € |
2 561 - 11 116 | 3,6 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku