dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
12 úsekov |
120,0 km |
2 - 8 |
1 385 m |
1 654 mil. € |
3,8 |
3,4 |
|||||||
1 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 0 m | 234 mil. € | 2 | 1 | ||||
2 | 6. | 7/2023 | R2 | 6,8 km | 4 | 0 m | 171 mil. € | 3 | 3 | ||||
3 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 0 m | 191 mil. € | 3 | 3 | ||||
4 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 0 m | 112 mil. € | 2 | 4 | ||||
5 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 0 m | 93 mil. € | 5 | 5 | ||||
6 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 0 m | 73 mil. € | 5 | 4 | ||||
7 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 0 m | 133 mil. € | 4 | 3 | ||||
8 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 0 m | 124 mil. € | 3 | 3 | ||||
9 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 0 m | 101 mil. € | 4 | 3 | ||||
10 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 385 m | 176 mil. € | 5 | 5 | ||||
11 | 47. | 7/2029 | R2 | 14,0 km | 2 | 0 m | 117 mil. € | 5 | 4 | ||||
12 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 0 m | 129 mil. € | 4 | 3 | ||||
12 úsekov |
120,0 km |
2 - 8 |
1 385 m |
1 654 mil. € |
3,8 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku