dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 0 m | 449 m | 112 mil. € | 2 | 4 | 9/2025 | 90. | ||||
2 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 0 m | 164 m | 129 mil. € | 4 | 3 | 11/2025 | 95. | ||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 385 m | 226 m | 176 mil. € | 5 | 5 | 1/2026 | 79. | ||||
4 | 47. | 7/2029 | R2 | 14,0 km | 2 | 0 m | 123 m | 117 mil. € | 5 | 4 | 7/2026 | 69. | ||||
5 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 0 m | 93 mil. € | 5 | 5 | 9/2026 | 89. | |||||
6 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 0 m | 86 m | 133 mil. € | 4 | 3 | 5/2027 | 91. | ||||
7 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 0 m | 137 m | 124 mil. € | 3 | 3 | 5/2027 | 45. | ||||
8 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 0 m | 199 m | 101 mil. € | 4 | 3 | 8/2027 | 80. | ||||
9 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 0 m | 433 m | 191 mil. € | 3 | 3 | 9/2029 | 11. | ||||
10 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 0 m | 1 130 m | 553 mil. € | 5 | 5 | 70. | |||||
10 úsekov |
166,0 km |
2 - 4 |
1 385 m |
2 946 m |
1 729 mil. € |
4,0 |
3,8 |
11. - 95. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku