dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 12,1 % | 2 | 1 606 m | 112 mil. € | 2 | 4 | |||
2 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 11,0 % | 2 | 1 074 m | 93 mil. € | 5 | 5 | |||
3 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | |||||||
4 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 36,3 % | 2 | 2 993 m | 133 mil. € | 4 | 3 | |||
5 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 7,3 % | 4 | 1 456 m | 191 mil. € | 3 | 3 | |||
6 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 24,3 % | 2 | 1 963 m | 124 mil. € | 3 | 3 | |||
7 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 17,0 % | 2 | 1 216 m | 101 mil. € | 4 | 3 | |||
8 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 9,7 % | 2 | 1 965 m | 176 mil. € | 5 | 5 | |||
9 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 5,5 % | 2 | 891 m | 117 mil. € | 5 | 4 | |||
10 | 42. - 43. | 11/2028 | ![]() | R4 | 7,9 km | 57,5 % | 2 | 4 710 m | 129 mil. € | 4 | 3 | |||
10 úsekov |
99,2 km |
16,9 % |
2 - 6 |
17 873 m |
1 176 mil. € |
3,6 |
3,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku