dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 2 | 4 | ||||
2 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 6 651 - 9 113 | 2 | 3 | ||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | ||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | ||||
5 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | ||||
6 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 3 | 3 | ||||
7 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | ||||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | ||||
93,4 km |
2 - 4 |
1 163 mil. € |
3 769 - 18 874 | 3,7 |
3,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku