plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
11 úsekov |
176,9 km |
2 - 4 |
1 858 mil. € |
1 065 - 18 874 | 3,9 |
3,6 |
3/2028 - po 2040 |
|||||||
1 | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 1 824 - 2 207 | 2 | 4 | 3/2028 | |||||
2 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 1 003 - 1 696 | 4 | 3 | 11/2028 | |||||
3 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 1 146 - 1 203 | 5 | 5 | 2/2029 | |||||
4 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 1 335 - 1 725 | 5 | 4 | 7/2029 | |||||
5 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 1 253 - 1 628 | 5 | 5 | 9/2029 | |||||
6 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 733 - 1 326 | 4 | 3 | 5/2030 | |||||
7 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 1 529 - 1 844 | 3 | 3 | 5/2030 | |||||
8 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 1 697 - 2 149 | 4 | 3 | 5/2030 | |||||
9 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 025 - 3 385 | 3 | 3 | 6/2031 | |||||
10 | R3 | 10,9 km | 2 | 129 mil. € | 5 586 - 10 745 | 1 352 - 2 228 | 3 | 2 | 8/2031 | |||||
11 | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 215 - 1 012 | 5 | 5 | po 2040 | |||||
11 úsekov |
176,9 km |
2 - 4 |
1 858 mil. € |
1 065 - 18 874 | 3,9 |
3,6 |
3/2028 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku