dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 11,7 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 (+5,1) | ||||||
2 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | Dolné Semerovce | 63 mil. € | 3,9 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2030 (+5,2) | |||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 10,1 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||||
4 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené | 305 mil. € | 5,0 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5,5 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||||
5 úsekov |
97,2 km |
2 - 4 |
1 616 mil. € |
36,2 mil. € |
5 189 - 21 743 | 3,2 |
3,0 |
5/2029 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku