dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 10. | 4/2024 | D1 | 3,8 km | 2 | 1 030 m | 57 mil. € | 10 312 | 3 | 5 | 4/2027 (+4,1) | ||||||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 739 m | Gombasek | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 017 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
4 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 641 m | Sklené | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 2 587 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||||
5 úsekov |
90,8 km |
2 |
9 014 m |
1 301 mil. € |
3 782 - 14 648 | 3,8 |
4,0 |
4/2027 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku