dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Dolný Štál | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||||
2 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | ||||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||||
5 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||||
6 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||||
6 úsekov |
133,2 km |
2 |
1 714 mil. € |
5 189 - 14 648 | 4,0 |
3,8 |
4/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku