plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||
27 úsekov |
275,5 km |
2 - 6 |
5 092 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 | |||||
1 | D1 | 19,9 km | 6 | 321 mil. € | 3 862 - 4 344 | 3 | 2 | 9/2032 (+5,6) | |||
2 | D1 | 14,4 km | 4 | 241 mil. € | 102 - 937 | 2 | 2 | 12/2019 | |||
3 | R2 | 6,2 km | 2 | 105 mil. € | 954 | 2 | 2 | 3/2026 (+4,7) | |||
4 | D1 | 18,2 km | 4 | 192 mil. € | 911 - 840 | 2 | 2 | 8/2036 (+7,9) | |||
5 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | ||||
6 | R3 | 8,7 km | 2 | 94 mil. € | 919 | 4 | 2 | 8/2034 (+2,1) | |||
7 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||
8 | D4 | 22,6 km | 4 - 6 | 3 640 - 7 825 | 1 | 2 | 11/2021 (+0,4) | ||||
9 | R3 | 6,5 km | 2 | 70 mil. € | 1 175 - 1 262 | 2 | 2 | 7/2026 (+2,7) | |||
10 | D1 | 13,5 km | 4 | 555 mil. € | 1 602 - 4 842 | 1 | 2 | 2024 (+4,0) | |||
11 | R4 | 4,0 km | 4 | 105 mil. € | 1 651 | 2 | 2 | 8/2029 (+3,8) | |||
12 | R6 | 11,2 km | 2 | 182 mil. € | 632 | 4 | 3 | 7/2033 (+4,3) | |||
13 | R2 | 16,0 km | 4 | 277 mil. € | 1 577 - 2 085 | 2 | 2 | 10/2028 (+3,2) | |||
14 | R2 | 13,5 km | 4 | 142 mil. € | 1 474 - 1 473 | 2 | 2 | 2021 (+1,1) | |||
15 | R3 | 10,9 km | 2 | 129 mil. € | 791 - 1 514 | 3 | 2 | 8/2034 (+2,1) | |||
16 | D3 | 4,0 km | 4 | 179 mil. € | 3 812 | 1 | 2 | 11/2030 (+6,4) | |||
17 | D1 | 7,9 km | 4 | 434 mil. € | 1 935 - 2 218 | 1 | 2 | 7/2021 (0,0) | |||
18 | R3 | 10,3 km | 2 | 92 mil. € | 1 155 - 1 257 | 4 | 2 | po 2040 (0,0) | |||
19 | R4 | 7,0 km | 2 | 122 mil. € | 1 298 - 1 289 | 2 | 2 | 6/2030 (+3,7) | |||
20 | R2 | 14,1 km | 2 | 272 mil. € | 714 - 765 | 3 | 2 | 12/2029 (+5,4) | |||
21 | D3 | 12,3 km | 2 | 377 mil. € | 216 - 455 | 2 | 2 | 6/2017 | |||
22 | R3 | 4,4 km | 2 | 70 mil. € | 1 307 - 1 203 | 2 | 2 | 8/2022 (+2,2) | |||
23 | R2 | 8,3 km | 2 | 169 mil. € | 977 - 1 002 | 2 | 2 | 8/2026 (+5,1) | |||
24 | R2 | 17,5 km | 4 | 287 mil. € | 1 901 - 3 009 | 2 | 2 | 7/2034 (+10,0) | |||
25 | D3 | 5,7 km | 4 | 269 mil. € | 3 351 - 3 914 | 1 | 2 | 2021 (+0,5) | |||
26 | R3 | 5,0 km | 2 | 63 mil. € | 1 111 - 1 112 | 3 | 2 | 11/2030 (+5,2) | |||
27 | D3 | 4,3 km | 4 | 269 mil. € | 4 356 - 4 665 | 4 | 2 | 12/2017 | |||
27 úsekov |
275,5 km |
2 - 6 |
5 092 mil. € |
2,2 |
2,0 |
6/2017 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku