dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
24 úsekov |
237,2 km |
2 - 6 |
38 |
4 081 mil. € |
2,1 |
2,1 |
12/2020 - 10/2021 |
|||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 1 | 555 mil. € | 1 | 2 | ||||||
2 | 6/2017 | D1 | 7,9 km | 4 | 2 | 434 mil. € | 1 | 2 | 10/2021 | |||||
3 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 2 | 321 mil. € | 3 | 2 | dopravné, TEN-T | ||||
4 | 59. | 7/2031 | R2 | 17,5 km | 4 | 2 | 287 mil. € | 2 | 2 | |||||
5 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 | 277 mil. € | 2 | 2 | ostatné | ||||
6 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 2 | 272 mil. € | 3 | 2 | ostatné | ||||
7 | 12/2016 | D3 | 5,7 km | 4 | 2 | 269 mil. € | 1 | 2 | 12/2020 (0,0) | |||||
8 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 2 | 192 mil. € | 2 | 2 | TEN-T | ||||
9 | 31. | 11/2026 | D3 | 4,0 km | 4 | 0 | 179 mil. € | 1 | 2 | dopravné, TEN-T | ||||
10 | 13. | 8/2024 | R2 | 8,3 km | 2 | 2 | 169 mil. € | 2 | 2 | ostatné | ||||
11 | 8/2019 | R2 | 13,5 km | 4 | 1 | 142 mil. € | 2 | 2 | ||||||
12 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 4 | 129 mil. € | 3 | 2 | ostatné | ||||
13 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 1 | 122 mil. € | 2 | 2 | ostatné | ||||
14 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 0 | 105 mil. € | 2 | 2 | ostatné | ||||
15 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 1 | 105 mil. € | 2 | 2 | dopravné | ||||
16 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 2 | 94 mil. € | 4 | 2 | ostatné | ||||
17 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 0 | 92 mil. € | 4 | 2 | variant TEN-T | ||||
18 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 | 77 mil. € | 2 | 2 | ostatné | ||||
19 | 12. | 7/2024 | R3 | 6,5 km | 2 | 1 | 70 mil. € | 2 | 2 | ostatné | ||||
20 | 3/2021 | R3 | 4,4 km | 2 | 2 | 70 mil. € | 2 | 2 | ||||||
21 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 1 | 63 mil. € | 3 | 2 | TEN-T | ||||
22 | 10. | 4/2024 | D1 | 3,8 km | 2 | 0 | 57 mil. € | 3 | 5 | |||||
23 | 7/2016 | D4 | 4,4 km | 4 - 6 | 2 | 1 | 2 | |||||||
24 | 7/2016 | D4 | 22,6 km | 4 - 6 | 6 | 1 | 2 | |||||||
24 úsekov |
237,2 km |
2 - 6 |
38 |
4 081 mil. € |
2,1 |
2,1 |
12/2020 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku