dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
246,0 km |
2 - 6 |
25 147 m |
4 188 mil. € |
2,2 |
2,1 |
|||||||
1 | 6/2014 | 13,5 km | 4 | D 26,5/100 | 2 365 m | 555 mil. € | 1 | 2 | ||||
2 | 7/2016 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 | 2 | ||||||
3 | 7/2016 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 | 2 | ||||||
4 | 6/2017 | 7,9 km | 4 | D 26,5/100 | 1 863 m | 434 mil. € | 1 | 2 | 10/2021 | |||
5 | 8/2019 | 13,5 km | 4 | R 24,5/100 | 1 631 m | 142 mil. € | 2 | 2 | ||||
6 | 3/2021 | 4,4 km | 2 | R 24,5/100 v polovičnom profile | 1 568 m | 70 mil. € | 2 | 2 | ||||
7 | 8. - 9. | 3/2024 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 343 m | 105 mil. € | 2 | 2 | |||
8 | 12. | 7/2024 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 463 m | 70 mil. € | 2 | 2 | |||
9 | 13. | 8/2024 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 401 m | 169 mil. € | 2 | 2 | |||
10 | 16. - 17. | 12/2024 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 035 m | 272 mil. € | 3 | 2 | |||
11 | 20. - 23. | 10/2025 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 1 544 m | 77 mil. € | 2 | 2 | |||
12 | 20. - 23. | 10/2025 | 16,0 km | 4 | R 24,5/120(100) | 1 433 m | 277 mil. € | 2 | 2 | |||
13 | 25. | 1/2026 | 10,8 km | 4 | D 24,5/80 (100) | 1 256 m | 309 mil. € | 2 | 4 | |||
14 | 28. - 29. | 8/2026 | 4,0 km | 4 | R 24,5/100 | 1 468 m | 105 mil. € | 2 | 2 | |||
15 | 31. | 11/2026 | 4,0 km | 4 | D 24,5/80 | 624 m | 179 mil. € | 1 | 2 | |||
16 | 34. - 36. | 6/2027 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 1 721 m | 122 mil. € | 2 | 2 | |||
17 | 39. - 40. | 3/2028 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 3 | 2 | ||||
18 | 42. - 43. | 11/2028 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 652 m | 63 mil. € | 3 | 2 | |||
19 | 50. - 52. | 5/2030 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 1 826 m | 124 mil. € | 3 | 3 | |||
20 | 59. | 7/2031 | 17,5 km | 4 | R 24,5/100 | 2 230 m | 287 mil. € | 2 | 2 | |||
21 | 60. - 61. | 8/2031 | 8,7 km | 2 | R 11,5/80 (60) | 178 m | 94 mil. € | 4 | 2 | |||
22 | 60. - 61. | 8/2031 | 10,9 km | 2 | R 11,5/80 (60) | 1 040 m | 129 mil. € | 3 | 2 | |||
23 | 64. - 68. | 8/2033 | 18,2 km | 4 | D 26,5/120
(100) | 412 m | 192 mil. € | 2 | 2 | |||
24 | 71. - 78. | po 2040 | 10,3 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 95 m | 92 mil. € | 4 | 2 | |||
246,0 km |
2 - 6 |
25 147 m |
4 188 mil. € |
2,2 |
2,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku