dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
235,2 km |
2 - 6 |
15 064 m |
3 879 mil. € |
2,2 |
2,0 |
||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 7 445 m | 555 mil. € | 10 992 | 1 | 2 | ||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | 0 m | 1 | 2 | ||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | 0 m | 1 | 2 | ||||||
4 | 6/2017 | D1 | 7,9 km | 4 | 2 237 m | 434 mil. € | 1 | 2 | 10/2021 | ||||
5 | 8/2019 | R2 | 13,5 km | 4 | 0 m | 142 mil. € | 2 | 2 | |||||
6 | 3/2021 | R3 | 4,4 km | 2 | 0 m | 70 mil. € | 2 165 | 2 | 2 | ||||
7 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 0 m | 105 mil. € | 2 002 | 2 | 2 | |||
8 | 12. | 7/2024 | R3 | 6,5 km | 2 | 0 m | 70 mil. € | 1 489 | 2 | 2 | |||
9 | 13. | 8/2024 | R2 | 8,3 km | 2 | 0 m | 169 mil. € | 2 147 | 2 | 2 | |||
10 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 4 282 m | 272 mil. € | 3 | 2 | ||||
11 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 1 390 | 2 | 2 | |||
12 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 510 m | 277 mil. € | 7 394 - 8 906 | 2 | 2 | |||
13 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 0 m | 105 mil. € | 2 382 | 2 | 2 | |||
14 | 31. | 11/2026 | D3 | 4,0 km | 4 | 590 m | 179 mil. € | 7 452 | 1 | 2 | |||
15 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 0 m | 122 mil. € | 1 908 | 2 | 2 | |||
16 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 0 m | 321 mil. € | 3 | 2 | ||||
17 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 0 m | 63 mil. € | 574 | 3 | 2 | |||
18 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 0 m | 124 mil. € | 2 113 | 3 | 3 | |||
19 | 59. | 7/2031 | R2 | 17,5 km | 4 | 0 m | 287 mil. € | 2 879 | 2 | 2 | |||
20 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 0 m | 94 mil. € | 1 760 | 4 | 2 | |||
21 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 0 m | 129 mil. € | 2 343 | 3 | 2 | |||
22 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 0 m | 192 mil. € | 3 049 | 2 | 2 | |||
23 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 0 m | 92 mil. € | 4 | 2 | ||||
235,2 km |
2 - 6 |
15 064 m |
3 879 mil. € |
2,2 |
2,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku