dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
25 úsekov |
298,9 km |
2 - 6 |
5 700 mil. € |
3,8 |
3,4 |
10/2028 - 6/2036 |
10. - 98. | ||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | 35. | |||
2 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
3 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 2 | 2 | 6/2030 (+3,7) | 32. | |||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 2/2031 (+4,1) | 98. | |||
5 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 9/2032 (+5,6) | 10. | |||
6 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 2/2032 (+4,9) | 79. | |||
7 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||
8 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 3 | 3 | 9/2033 (+5,8) | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 7/2032 (+5,3) | 69. | |||
10 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 5 | 5 | 9/2032 (+5,6) | 89. | |||
11 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 9/2032 (+4,1) | 11. | |||
12 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | 5/2033 (+6,1) | 91. | |||
13 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 | 3 | 5/2033 (+6,1) | 45. | |||
14 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 4 | 3 | 5/2033 (+6,1) | 80. | |||
15 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 7/2033 (+4,3) | 17. | |||
16 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 7/2033 (+4,3) | 14. | |||
17 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 5/2033 (+10,2) | 11. | |||
18 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 5/2033 (+10,2) | 11. | |||
19 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | 6/2036 (+2,3) | 57. | |||
20 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 6/2034 (+7,0) | 11. | |||
21 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 7/2034 (+10,0) | ||||
22 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 4 | 2 | 8/2034 (+2,1) | 82. | |||
23 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 3 | 2 | 8/2034 (+2,1) | 63. | |||
24 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 10/2035 (+5,6) | ||||
25 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||
25 úsekov |
298,9 km |
2 - 6 |
5 700 mil. € |
3,8 |
3,4 |
10/2028 - 6/2036 |
10. - 98. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku