plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | D1 | 14,9 km | 4 | 341 mil. € | 12 491 - 24 900 | 449 - 869 | 1 | 1 | 2023 (+1,0) | ||||||
2 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 408 | 2 | 2 | 8/2029 (+3,8) | ||||||
3 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 299 - 336 | 3 | 5 | 6/2016 | 12/2029 (+2,8) | |||||
4 | R4 | 6,5 km | 2 | 116 mil. € | 6 651 - 9 113 | 140 - 156 | 2 | 3 | 6/2030 (+3,7) | ||||||
5 | R4 | 7,0 km | 2 | 122 mil. € | 3 407 - 3 769 | 95 - 124 | 2 | 2 | 6/2030 (+3,7) | ||||||
6 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 178 | 5 | 4 | 9/2009 | 2/2031 (+4,1) | |||||
7 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 459 - 530 | 3 | 2 | 12/2009 | 9/2032 (+5,6) | ||||
8 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 393 | 2 | 4 | 10/2004 | 9/2031 (+5,4) | |||||
9 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 541 | 3 | 3 | 8/2013 | 9/2033 (+5,8) | |||||
10 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 480 - 650 | 2 | 2 | 11/2008 | 7/2034 (+10,0) | |||||
10 úsekov |
114,5 km |
2 - 6 |
2 145 mil. € |
3 407 - 54 519 | 2,5 |
2,8 |
7/2023 - 7/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku