plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | ![]() | R4 | 4,0 km | 4 | 578 m | Lipníky | 105 mil. € | 6,4 mil. € | 14 625 | 2 | 2 | ||||
2 | ![]() | R2 | 18,0 km | 2 | 1 015 m | Moldava nad Bodvou, Šaca | 224 mil. € | 6,8 mil. € | 10 140 - 11 010 | 3 | 5 | ||||
3 | ![]() | R4 | 6,5 km | 2 | 101 m | Kuková | 116 mil. € | 6,2 mil. € | 6 651 - 9 113 | 2 | 3 | ||||
4 | ![]() | R4 | 7,0 km | 2 | 227 m | Okrúhle | 122 mil. € | 5,7 mil. € | 3 407 - 3 769 | 2 | 2 | ||||
5 | ![]() | R2 | 7,8 km | 2 | Jablonov n.Turňou | 73 mil. € | 3,3 mil. € | 5 587 | 5 | 4 | |||||
6 | ![]() | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 4,8 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | ||||
7 | ![]() | R2 | 11,5 km | 2 | 214 m | 235 mil. € | 6,1 mil. € | 7 793 | 2 | 4 | |||||
8 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 11,9 mil. € | 10 359 | 3 | 3 | ||||||
9 | ![]() | R2 | 17,5 km | 4 | 228 m | Rákoš, Zvolenská Slatina | 287 mil. € | 8,7 mil. € | 12 819 - 29 988 | 2 | 2 | ||||
10 | ![]() | D2 | 6,9 km | 6 | Stupava | 107 mil. € | 2,6 mil. € | 5 | 5 | ||||||
106,4 km |
2 - 6 |
2 363 m |
1 911 mil. € |
62,5 mil. € |
3 407 - 54 519 | 2,9 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku