dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 875 - 929 | 2 | 4 | ||||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 2 765 - 3 271 | 3 | 2 | ||||
3 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 655 | 2 | 4 | ||||
4 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 333 - 812 | 3 | 5 | ||||
5 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 2 277 | 5 | 5 | ||||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | |||||
7 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | |||||
8 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 525 - 852 | 4 | 4 | ||||
175,5 km |
2 - 6 |
3 049 mil. € |
3,4 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku