dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 | ||||||
2 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2021 | ||||
3 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1/2027 | |||
4 | 8. - 9. | 3/2024 | ![]() | R7 | 9,4 km | 4 | 191 mil. € | 6 428 - 9 084 | 4 | 5 | 9/2028 | |||
5 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 | |||
6 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 | ||||
7 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 9/2032 | ||
8 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 | ||||
93,7 km |
4 - 6 |
2 126 mil. € |
6 428 - 93 344 | 2,4 |
3,0 |
11/2021 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku