dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 1/2015 | ||||||||
2 | 31. | 11/2026 | D3 | 4,0 km | 4 | 624 m | 179 mil. € | 15 053 | 1 | 2 | 8/2013 | 31 | |||||
3 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 4 086 m | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 5/2025 | 37 | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 397 m | 73 mil. € | 5 587 | 5 | 4 | 3/2022 | 38 | |||||
5 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 1 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 5/2013 | 39 | ||||
6 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 1 157 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 9/2013 | 40 | |||||
7 | 41. | 9/2028 | R2 | 11,5 km | 2 | 2 549 m | 1 | 235 mil. € | 7 793 | 2 | 4 | 5/2013 | 41 | ||||
8 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 4 546 m | 1 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 12/2023 | 42 | ||||
9 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 652 m | 1 | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 4/2025 | 43 | ||||
103,2 km |
2 - 6 |
14 011 m |
4 |
1 896 mil. € |
2 552 - 93 344 | 2,7 |
2,9 |
31 - 43 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku