dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 9/2032 (+5,6) | ||||
2 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5,9 % (Kapušany - V. Komárnik) | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 5,8 % (Martin - Horná Štubňa) | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | ||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | |||||
6 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | po 2040 (0,0) | |||||
6 úsekov |
136,1 km |
2 - 6 |
2 447 mil. € |
2 228 - 54 519 | 3,7 |
3,5 |
9/2032 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku