dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2026 (+3,7) | ||||
2 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 7/2026 (+2,7) | ||||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | |||||
4 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | ||||
5 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 10/2028 (+4,2) | ||||
6 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 12/2028 (+4,3) | ||||
7 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 9/2032 (+5,6) | |||
8 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||
9 | 71. - 78. | po 2040 | ![]() | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | po 2040 (0,0) | ||||
9 úsekov |
97,0 km |
2 - 6 |
1 492 mil. € |
2 156 - 54 519 | 2,9 |
3,1 |
4/2026 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku