dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
pôvodný zmluvný termín
|
+ posun v rokoch
za posledné cca 4 roky |
||||||
1 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 9/2032 (+5,6) | ||||
2 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 3/2031 (+5,9) | ||||
3 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 2/2031 (+4,1) | ||||
5 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 9/2031 (+5,4) | ||||
6 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 3/2023 | 2023 (+2,0) | ||||
7 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 2/2031 (+6,9) | ||||
8 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 3 | 2 | 11/2030 (+5,2) | ||||
8 úsekov |
87,0 km |
2 - 6 |
2 073 mil. € |
2,8 |
3,1 |
7/2023 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku