dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
1 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | ||||
2 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 3 | 3 | ||||
3 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | ||||
4 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | |||
5 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 2 | 4 | ||||
6 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 2 | 4 | ||||
7 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | ||||
8 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 9 492 - 10 279 | 3 | 2 | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | ||||
10 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | |||
107,3 km |
2 - 6 |
2 018 mil. € |
2 552 - 54 519 | 3,5 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku