dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | |||
2 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 4 | |||||
3 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | Valaská Dubová, Likavka | 94 mil. € | 7 211 | 4 | 2 | ||||
4 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | Sobrance | 139 mil. € | 4 033 - 8 369 | 4 | 3 | ||||
5 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | 2 | ||||
6 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 5 586 - 10 745 | 3 | 2 | ||||
7 | 13. | 8/2024 | ![]() | R2 | 8,3 km | 2 | Zacharovce, Bátka | 169 mil. € | 5 277 - 6 250 | 2 | 2 | ||||
8 | 59. | 7/2031 | ![]() | R2 | 17,5 km | 4 | Rákoš, Zvolenská Slatina | 287 mil. € | 12 819 - 29 988 | 2 | 2 | ||||
8 úsekov |
120,6 km |
2 - 6 |
1 643 mil. € |
4 033 - 54 519 | 3,0 |
2,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku