dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané |
prebratie
| ||||||||||
248,7 km |
13,3 % |
2 - 6 |
5 633 mil. € |
3 769 - 54 519 | 3,4 |
||||||||||
1 | 3/2020 | ![]() | R2 | 9,1 km | 27,9 % | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 8 780 - 11 203 | 4 | 7/2014 | ||||
2 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 22,9 % | 4 | R 24,5/100 | 171 mil. € | 11 764 - 50 895 | 3 | 12/2014 | |||
3 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 27,0 % | 2 | R 11,5/80 | 57 mil. € | 10 312 | 5 | ||||
4 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 7,3 % | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 5 792 - 7 064 | 2 | 4/2015 | |||
5 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 5,5 % | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 4 001 | 3 | 12/2014 | |||
6 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 5,4 % | 4 | R 24,5/120(100) | 59 mil. € | 12 862 | 4 | 9/2014 | |||
7 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 24,1 % | 4 | R 24,5/120(100) | 143 mil. € | 12 157 | 4 | 9/2014 | |||
8 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 4 | 9/2009 | |||||
9 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2,5 % | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 10 140 - 11 010 | 5 | 12/2014 | |||
10 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 27,4 % | 4 | R 24,5/80 | 785 mil. € | 8 140 - 13 204 | 3 | 8/2015 | |||
11 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 42 774 - 54 519 | . . . | 2 | ||||
12 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 13,1 % | 2 | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 9 492 - 10 279 | 2 | 5/2015 | |||
13 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 24,3 % | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 769 - 3 897 | 3 | 12/2014 | |||
14 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 5 | |||||
15 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 7,3 % | 4 | R 24,5/120 (100) | 191 mil. € | 14 233 - 18 874 | 3 | 2/2016 | |||
16 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 9,5 % | 2 | R 11,5/80 (60) | 129 mil. € | 5 586 - 10 745 | 2 | ||||
17 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 1,3 % | 4 | D 26,5/120
(100) | 418 mil. € | 9 503 - 9 802 | 3 | 8/2014 | |||
18 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 3,2 % | 4 | D 26,5/120
(100) | 162 mil. € | 10 444 - 14 783 | 3 | 8/2014 | |||
19 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 18,9 % | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 2/2016 | ||||
20 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 55,2 % | 2 | R 11,5/70 | 54 mil. € | 7 972 | 4 | ||||
248,7 km |
13,3 % |
2 - 6 |
5 633 mil. € |
3 769 - 54 519 | 3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku