dátum |
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 3/2020 | R2 | 9,1 km | 212 m | 267 mil. € | 8 780 - 11 203 | 751 - 846 | 3 | 4 | 2024 (+2,8) | |||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 86 m | 133 mil. € | 5 814 - 7 518 | 384 - 424 | 4 | 3 | 5/2033 (+6,1) | ||||
3 | 28. - 29. | 8/2026 | R4 | 4,0 km | 578 m | 105 mil. € | 14 625 | 888 | 2 | 2 | 8/2029 (+3,8) | ||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 440 m | 182 mil. € | 7 234 | 426 | 4 | 3 | 7/2033 (+4,3) | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 137 m | 124 mil. € | 3 769 - 3 897 | 240 - 264 | 3 | 3 | 5/2033 (+6,1) | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 199 m | 101 mil. € | 3 782 - 6 302 | 205 - 412 | 4 | 3 | 5/2033 (+6,1) | ||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 265 m | 222 mil. € | 2 561 - 5 054 | 146 - 252 | 4 | 3 | 7/2033 (+4,3) | ||||
7 úsekov |
57,1 km |
1 917 m |
1 134 mil. € |
2 561 - 14 625 | 3,4 |
3,0 |
7/2024 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku