dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | Prešov - sever | 179 mil. € | 15 837 - 18 098 | 964 - 1 246 | 1 | 3 | 2/2015 | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | Mýtna | 142 mil. € | 5,0 min. | 9 007 - 9 998 | 1 474 - 1 473 | 2 | 2 | 7/2010 | |||||
3 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | Nováky - západ | 112 mil. € | 8 634 - 11 116 | 1 189 - 1 517 | 2 | 4 | 7/2011 | |||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | Kuková | 133 mil. € | 2,6 min. | 5 814 - 7 518 | 349 - 902 | 4 | 3 | 7/2024 | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | Giraltovce | 124 mil. € | 3,6 min. | 3 769 - 3 897 | 1 289 - 1 580 | 3 | 3 | 7/2024 | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | Stročín | 101 mil. € | 1,2 min. | 3 782 - 6 302 | 1 492 - 1 737 | 4 | 3 | 7/2024 | ||||
7 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | Púchov západ,
Púchov východ,
Dolné Kočkovce | 182 mil. € | 7 234 | 632 | 4 | 3 | 3/2025 | |||||
8 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | Mestečko | 222 mil. € | 2 561 - 5 054 | 427 - 551 | 4 | 3 | 3/2025 | |||||
71,3 km |
2 - 4 |
1 195 mil. € |
12,4 min. |
2 561 - 18 098 | 3,0 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku