dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | ||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 1 | |||||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 5,0 min. | 11,5 min. | 9 007 - 9 998 | 2 | |||||
3 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2,8 min. | 5,5 min. | 2 | |||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 2,6 min. | 8,0 min. | 5 814 - 7 518 | 4 | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3,6 min. | 8,0 min. | 3 769 - 3 897 | 3 | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 1,2 min. | 5,0 min. | 3 782 - 6 302 | 4 | ||||
7 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 4 | ||||||
8 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | ||||||
66,7 km |
2 - 4 |
1 160 mil. € |
15,3 min. |
38,0 min. |
2 561 - 18 098 | 3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku