dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | |||||||||
1 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 1 401 m | 202 mil. € | 10 088 - 50 895 | 2 | |||
2 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 1 221 m | 179 mil. € | 15 837 - 18 098 | 1 | ||||
3 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 1 456 m | 191 mil. € | 14 233 - 18 874 | 3 | |||
4 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 1 703 m | 70 mil. € | 10 334 - 11 542 | 2 | ||||
5 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 2 725 m | 171 mil. € | 11 764 - 50 895 | 3 | |||
6 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 16 837 m | 224 mil. € | 10 140 - 11 010 | 3 | |||
7 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 9 007 - 9 998 | 2 | ||||
8 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 10 359 | 3 | |||
82,6 km |
2 - 4 |
27 634 m |
1 501 mil. € |
9 007 - 50 895 | 2,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku