dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
odhad INEKO
|
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 2 | 1 | 10/2024 (+2,6) | |||||||
2 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 (+4,3) | |||||||
3 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | ||||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | |||||||
5 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 11/2022 | 2021 (+1,1) | |||||||
6 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 3/2023 | 2023 (+2,0) | |||||||
7 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 2 | 2 | 6/2023 | 8/2022 (+2,2) | |||||||
7 úsekov |
65,8 km |
2 - 6 |
1 046 mil. € |
9 007 - 50 895 | 2,6 |
2,7 |
11/2022 - 6/2023 |
7/2021 - 10/2035 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku