dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 7/2019 | ![]() | R4 | 4,3 km | 26,8 % | 4 | R4 stred | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 10/2014 | |||||
2 | 8/2019 | ![]() | R2 | 13,5 km | 0,0 % | 4 | R2 stred | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 12/2017 | |||||
3 | 3/2021 | ![]() | R3 | 4,4 km | 0,0 % | 2 | R3 sever (Orava) | 70 mil. € | 10 334 - 11 542 | 2 | 2 | 2/2011 | |||||
4 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 0,0 % | 4 | R2 východ, R4 juh | 202 mil. € | 10 088 - 50 895 | 2 | 1 | 7/2018 | ||||
5 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 0,0 % | 4 | R2 východ | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 8/2018 | ||||
6 | 34. - 36. | 6/2027 | ![]() | R4 | 6,5 km | 0,0 % | 2 | R4 sever | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2024 | ||||
7 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 32,1 % | 4 | R1 BB - RK | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 3/2024 | ||||
7 úsekov |
64,7 km |
9,2 % |
2 - 4 |
1 665 mil. € |
6 651 - 50 895 | 2,1 |
2,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku