dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 5/2021 | 11/2020 | ||||
2 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 8/2024 | 7/2025 | ||||
3 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 587 | 5 | 4 | 2/2026 | 11/2026 | ||||
4 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 7 234 | 4 | 3 | 2/2029 | 9/2029 | ||||
5 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 2/2029 | 9/2029 | ||||
5 úsekov |
61,2 km |
2 - 4 |
986 mil. € |
2 561 - 30 731 | 3,6 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku