dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
27 úsekov |
262,6 km |
2 - 4 |
41 881 m |
5 591 mil. € |
3,0 |
3,0 |
7/2020 - 8/2037 |
7/2020 - 1/2021 | |||||||
1 | 1/2014 | D1 | 11,3 km | 4 | 3 585 m | 517 mil. € | 2 | 3 | 2021 (+2,1) | 1/2021 (0,0) | |||||
2 | 7/2016 | R7 | 17,4 km | 4 | 2 | 3 | 7/2020 (+0,0) | 7/2020 (0,0) | |||||||
3 | 7/2019 | R4 | 4,3 km | 4 | 884 m | 179 mil. € | 1 | 3 | 12/2017 | 2023 (+2,0) | |||||
4 | 4. | 9/2022 | R4 | 10,2 km | 4 | 1 432 m | 299 mil. € | 1 | 3 | 11/2020 | 1/2027 (+4,8) | ||||
5 | 5. | 4/2023 | R1 | 8,1 km | 4 | 379 m | 173 mil. € | 2 | 3 | 12/2019 | 4/2026 (+3,7) | ||||
6 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 556 m | 171 mil. € | 3 | 3 | 11/2021 | 7/2026 (+4,3) | ||||
7 | 11. | 6/2024 | R1 | 2,7 km | 4 | 221 m | 155 mil. € | 4 | 3 | 8/2023 | 6/2026 (+3,5) | ||||
8 | 13. | 8/2024 | R2 | 8,3 km | 2 | 401 m | 169 mil. € | 2 | 2 | 8/2023 | 8/2026 (+5,1) | ||||
9 | 19. | 6/2025 | R4 | 8,2 km | 2 | 453 m | 94 mil. € | 3 | 3 | 3/2024 | 6/2027 (+4,7) | ||||
10 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 2 764 m | 199 mil. € | 2 | 3 | 11/2024 | 10/2028 (+4,1) | ||||
11 | 30. | 10/2026 | R1 | 4,6 km | 4 | 1 225 m | 100 mil. € | 4 | 3 | 12/2025 | 10/2028 (+3,5) | ||||
12 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 2 104 m | 116 mil. € | 2 | 3 | 4/2026 | 6/2030 (+3,7) | ||||
13 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 4 086 m | 785 mil. € | 3 | 3 | 4/2027 | 2/2031 (+6,9) | ||||
14 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 4 546 m | 129 mil. € | 4 | 3 | 9/2027 | 11/2031 (+4,8) | ||||
15 | 46. | 3/2029 | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 3 | 3 | 4/2028 | 9/2033 (+5,8) | ||||
16 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 820 m | 71 mil. € | 4 | 3 | 10/2028 | 9/2032 (+4,1) | ||||
17 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 2 907 m | 133 mil. € | 4 | 3 | 2/2029 | 5/2033 (+6,1) | ||||
18 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 1 826 m | 124 mil. € | 3 | 3 | 2/2029 | 5/2033 (+6,1) | ||||
19 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 017 m | 101 mil. € | 4 | 3 | 2/2029 | 5/2033 (+6,1) | ||||
20 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 2 970 m | 182 mil. € | 4 | 3 | 9/2029 | 7/2033 (+4,3) | ||||
21 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 3 310 m | 222 mil. € | 4 | 3 | 9/2029 | 7/2033 (+4,3) | ||||
22 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 1 024 m | 191 mil. € | 3 | 3 | 8/2030 | 6/2034 (+7,0) | ||||
23 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 165 m | 418 mil. € | 3 | 3 | 6/2032 | 8/2036 (+7,9) | ||||
24 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 180 m | 139 mil. € | 4 | 3 | 6/2032 | 8/2036 (+7,7) | ||||
25 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 383 m | 162 mil. € | 3 | 3 | 6/2032 | 8/2036 (+7,7) | ||||
26 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 343 m | 136 mil. € | 4 | 3 | 6/2032 | 8/2036 (+7,7) | ||||
27 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 2 641 m | 305 mil. € | 3 | 3 | 10/2033 | 8/2037 (+5,9) | ||||
27 úsekov |
262,6 km |
2 - 4 |
41 881 m |
5 591 mil. € |
3,0 |
3,0 |
7/2020 - 8/2037 |
7/2020 - 1/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku