dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
131,7 km |
2 - 4 |
36 671 m |
3 255 mil. € |
5 550 - 28 413 | 3,1 |
3,5 |
||||||||
1 | 1/2014 | ![]() | D1 | 11,3 km | 4 | 3 585 m | 517 mil. € | 23 579 - 28 413 | 2 | 3 | 1/2021 (0,0) | |||
2 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 1 544 m | 77 mil. € | 2 | 2 | ||||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 2 956 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | |||
4 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 1 929 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | |||
5 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 206 m | 59 mil. € | 12 862 | 3 | 4 | |||
6 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 1 640 m | 143 mil. € | 12 157 | 3 | 4 | |||
7 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 3 480 m | 211 mil. € | 6 969 - 10 726 | 4 | 4 | |||
8 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 1 295 m | 125 mil. € | 6 412 - 8 112 | 4 | 4 | |||
9 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 2 982 m | 100 mil. € | 11 611 | 4 | 3 | |||
10 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | |||||
11 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 16 837 m | 224 mil. € | 10 140 - 11 010 | 3 | 5 | |||
12 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | |||||
13 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 218 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | |||
131,7 km |
2 - 4 |
36 671 m |
3 255 mil. € |
5 550 - 28 413 | 3,1 |
3,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku