dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 1 074 m | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 2 907 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 2 970 m | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 1 826 m | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 017 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
6 | 59. | 7/2031 | R2 | 17,5 km | 4 | 2 230 m | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | ||||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 3 310 m | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||||
7 úsekov |
71,3 km |
2 - 4 |
15 334 m |
1 142 mil. € |
2 561 - 29 988 | 3,7 |
3,1 |
9/2032 - 7/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku