dátum |
plánovaný
|
odhad NDS
|
rok
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 3/2021 | R3 | 4,4 km | 2 | 135 m | 70 mil. € | 2030 | 10 334 - 11 542 | 2 | 2 | 8/2022 (+2,2) | |||||
2 | 1. | 10/2021 | R4 | 14,3 km | 4 | 365 m | 202 mil. € | 2025 | 10 088 - 50 895 | 2 | 1 | 10/2024 (+2,6) | ||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 86 m | 133 mil. € | 2030 | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 440 m | 182 mil. € | 2030 | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 137 m | 124 mil. € | 2030 | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 199 m | 101 mil. € | 2030 | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||
7 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 2030 | 4 | 4 | 4/2029 (+4,1) | ||||||
8 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 265 m | 222 mil. € | 2030 | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||
8 úsekov |
76,9 km |
2 - 4 |
1 627 m |
1 207 mil. € |
2 561 - 50 895 | 3,4 |
2,8 |
8/2022 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku