dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
159,8 km |
2 - 4 |
1 054 m |
3 477 mil. € |
3,1 |
3,3 |
|||||||||
1 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 81 - 144 | 1 | 1 | 7,0 | |||
2 | 8. - 9. | 3/2024 | ![]() | R2 | 6,2 km | 2 | 68 m | 105 mil. € | 53 | 2 | 2 | 8,0 | ||
3 | 8. - 9. | 3/2024 | ![]() | R7 | 9,4 km | 4 | 15 m | 191 mil. € | 4 - 92 | 4 | 5 | 6,0 | ||
4 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 168 | 3 | 5 | 8,0 | |||
5 | 11. | 6/2024 | ![]() | R1 | 2,7 km | 4 | 131 m | 155 mil. € | 194 | 4 | 3 | 6,0 | ||
6 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 428 m | 70 mil. € | 123 - 165 | 2 | 2 | 6,0 | ||
7 | 13. | 8/2024 | ![]() | R2 | 8,3 km | 2 | 57 m | 169 mil. € | 78 - 98 | 2 | 2 | 8,0 | ||
8 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 5,0 | ||||
9 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 6,0 | ||||
10 | 16. - 17. | 12/2024 | ![]() | R7 | 8,4 km | 4 | 161 mil. € | 32 - 113 | 4 | 5 | 5,0 | |||
11 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 20 - 78 | 3 | 2 | 8,0 | ||
12 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 295 m | 662 mil. € | 27 - 240 | 4 | 4 | 2,0 | ||
159,8 km |
2 - 4 |
1 054 m |
3 477 mil. € |
3,1 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku