dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 10 312 | 3 | 5 | 25,0 | 8/2023 | 4/2027 (+4,1) | |||||
2 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 14,8 | 2/2027 | 2/2031 (+4,1) | |||||
3 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 110 m | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 14,3 | 1/2029 | 9/2032 (+4,1) | ||||
4 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 428 m | 406 mil. € | 7 784 | 4 | 4 | 13,0 | 9/2030 | 5/2033 (+10,2) | ||||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 366 m | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 13,0 | 9/2030 | 5/2033 (+10,2) | ||||
6 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 25,0 | 8/2032 | 8/2036 (+7,9) | ||||
7 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 24,0 | 8/2032 | 8/2036 (+7,9) | ||||
8 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 213 m | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 24,0 | 8/2032 | 8/2036 (+7,7) | ||||
9 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 24,0 | 8/2032 | 8/2036 (+7,7) | ||||
10 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 24,0 | 8/2032 | 8/2036 (+7,7) | ||||
114,6 km |
2 - 4 |
2 035 m |
1 992 mil. € |
1 698 - 14 783 | 3,6 |
3,4 |
8/2023 - 8/2032 |
4/2027 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku