dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 254 - 2 069 | 1 | 2 | |||||
2 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 10 312 | 531 | 3 | 5 | ||||
3 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 875 - 929 | 2 | 4 | ||||
4 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 738 - 1 705 | 1 | 1 | ||||
5 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 018 | 1 | 2 | ||||
6 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 940 - 1 697 | 2 | 2 | ||||
7 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 476 - 755 | 5 | 5 | ||||
8 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 7 972 | 499 | 3 | 4 | ||||
65,7 km |
2 - 4 |
1 912 mil. € |
5 420 - 32 334 | 2,3 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku