plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
153,3 km |
2 - 4 |
1 972 mil. € |
3,0 |
2,5 |
||||||
1 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 8/2006 | |||
2 | R3 | 8,7 km | 2 | 94 mil. € | 4 | 2 | ||||
3 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 2/2020 | |||
4 | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | 11/2018 | |||
5 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 9/2010 | |||
6 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 5/2019 | |||
7 | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 8/2006 | |||
8 | R3 | 10,9 km | 2 | 129 mil. € | 3 | 2 | ||||
9 | R3 | 10,3 km | 2 | 92 mil. € | 4 | 2 | 9/2010 | |||
10 | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 8/2006 | |||
11 | R3 | 58,5 km | 2 | 611 mil. € | 4 | 4 | 11/2018 | |||
12 | R3 | 5,0 km | 2 | 63 mil. € | 3 | 2 | 11/2018 | |||
153,3 km |
2 - 4 |
1 972 mil. € |
3,0 |
2,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku