dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
5 - vysoko predražená, 1 - veľmi nízka
|
+ posun v rokoch
za posledné cca 4 roky |
|||||||
24 úsekov |
226,1 km |
2 - 8 |
33 |
4 225 mil. € |
1,6 |
1,8 |
11/2015 - 9/2025 | |||||||
1 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 1 | 149 mil. € | 1 | 1 | 9/2025 (+4,6) | |||
2 | 11/2016 | ![]() | D1 | 14,4 km | 4 | 3 | 241 mil. € | 2 | 2 | 2 | 12/2019 | |||
3 | 7/2016 | ![]() | R7 | 17,4 km | 4 | 2 | 2 | 3 | 1 | 7/2020 (+0,0) | ||||
4 | 1/2014 | ![]() | D1 | 11,3 km | 4 | 0 | 517 mil. € | 2 | 3 | 4 | 2021 (+2,1) | |||
5 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 3 | 341 mil. € | 1 | 1 | 1 | 2023 (+1,0) | |||
6 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 2 | 1 | 2 | 1 | 11/2021 (+0,4) | ||||
7 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 6 | 1 | 2 | 1 | 11/2021 (+0,4) | ||||
8 | 7/2016 | ![]() | R7 | 8,4 km | 4 | 1 | 1 | 1 | 1 | 7/2020 (–1,0) | ||||
9 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 3 | 202 mil. € | 2 | 1 | 10/2024 (+2,6) | |||
10 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 1 | 267 mil. € | 3 | 4 | 2024 (+2,8) | ||||
11 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 1 | 555 mil. € | 1 | 2 | 1 | 2024 (+4,0) | |||
12 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 1 | 142 mil. € | 2 | 2 | 2021 (+1,1) | ||||
13 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 1 | 179 mil. € | 1 | 3 | 2023 (+2,0) | ||||
14 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 2 | 434 mil. € | 1 | 2 | 4 | 7/2021 (0,0) | |||
15 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 1 | 1 | 1 | 1 | 10/2021 (+0,3) | ||||
16 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 0 | 39 mil. € | 1 | 1 | 2021 (+2,2) | ||||
17 | 12/2013 | ![]() | R2 | 10,4 km | 4 | 1 | 1 | 3 | 11/2015 | |||||
18 | 1/2014 | ![]() | R2 | 9,6 km | 2 | 2 | 1 | 3 | 10/2016 | |||||
19 | ![]() | D3 | 3,1 km | 85 mil. € | 6/2017 | |||||||||
20 | 10/2013 | ![]() | D3 | 12,3 km | 2 | 377 mil. € | 2 | 2 | 5 | 6/2017 | ||||
21 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 2 | 70 mil. € | 2 | 2 | 8/2022 (+2,2) | ||||
22 | 8/2014 | ![]() | R2 | 7,9 km | 4 | 88 mil. € | 1 | 1 | 1 | 5/2017 | ||||
23 | 12/2016 | ![]() | D3 | 5,7 km | 4 | 2 | 269 mil. € | 1 | 2 | 3 | 2021 (+0,5) | |||
24 | 6/2014 | ![]() | D3 | 4,3 km | 4 | 1 | 269 mil. € | 4 | 2 | 5 | 12/2017 | |||
24 úsekov |
226,1 km |
2 - 8 |
33 |
4 225 mil. € |
1,6 |
1,8 |
11/2015 - 9/2025 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku