dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
5 - vysoko predražená, 1 - veľmi nízka
| |||||||
33 úsekov |
2 - 8 |
6 515 mil. € |
2,6 |
2,9 |
|||||||||
1 | 5. | 4/2023 | R1 | 4 | 173 mil. € | 2 | 3 | 9,0 | |||||
2 | 34. - 36. | 6/2027 | D1 | 8 | 234 mil. € | 2 | 1 | 5,0 | |||||
3 | 8. - 9. | 3/2024 | R2 | 2 | 105 mil. € | 2 | 2 | 8,0 | |||||
4 | 20. - 23. | 10/2025 | R3 | 2 | 77 mil. € | 2 | 2 | 6,0 | |||||
5 | 14. - 15. | 10/2024 | R7 | 2 | 227 mil. € | 4 | 4 | 5,0 | |||||
6 | 34. - 36. | 6/2027 | R4 | 2 | 116 mil. € | 2 | 3 | 5,0 | |||||
7 | 8. - 9. | 3/2024 | R7 | 4 | 191 mil. € | 4 | 5 | 6,0 | |||||
8 | 6. | 7/2023 | R2 | 4 | 171 mil. € | 3 | 3 | 9,0 | |||||
9 | 24. | 12/2025 | R2 | 4 | 143 mil. € | 3 | 4 | 7,0 | |||||
10 | 12. | 7/2024 | R3 | 2 | 70 mil. € | 2 | 2 | 6,0 | |||||
11 | 25. | 1/2026 | D3 | 4 | 309 mil. € | 2 | 4 | 6,0 | |||||
12 | 19. | 6/2025 | R4 | 2 | 94 mil. € | 3 | 3 | 7,0 | |||||
13 | 28. - 29. | 8/2026 | R4 | 4 | 105 mil. € | 2 | 2 | 5,0 | |||||
14 | 26. | 4/2026 | R2 | 2 | 211 mil. € | 4 | 4 | 5,0 | |||||
15 | 16. - 17. | 12/2024 | R7 | 4 | 161 mil. € | 4 | 5 | 5,0 | |||||
16 | 20. - 23. | 10/2025 | R2 | 4 | 277 mil. € | 2 | 2 | 6,0 | |||||
17 | 32. - 33. | 12/2026 | R2 | 2 | 224 mil. € | 3 | 5 | 5,0 | |||||
18 | 20. - 23. | 10/2025 | R3 | 2 | 199 mil. € | 2 | 3 | 6,0 | |||||
19 | 31. | 11/2026 | D3 | 4 | 179 mil. € | 1 | 2 | 7,0 | |||||
20 | 28. - 29. | 8/2026 | R2 | 2 | 125 mil. € | 4 | 4 | 5,0 | |||||
21 | 4. | 9/2022 | R4 | 4 | 299 mil. € | 1 | 3 | 10,0 | |||||
22 | 10. | 4/2024 | D1 | 2 | 57 mil. € | 3 | 5 | 8,0 | |||||
23 | 18. | 4/2025 | D1 | 2 | 12 mil. € | 2 | 1 | 7,0 | |||||
24 | 34. - 36. | 6/2027 | R4 | 2 | 122 mil. € | 2 | 2 | 5,0 | |||||
25 | 16. - 17. | 12/2024 | R2 | 2 | 272 mil. € | 3 | 2 | 8,0 | |||||
26 | 11. | 6/2024 | R1 | 4 | 155 mil. € | 4 | 3 | 6,0 | |||||
27 | 30. | 10/2026 | R1 | 4 | 100 mil. € | 4 | 3 | 3,0 | |||||
28 | 20. - 23. | 10/2025 | R2 | 4 | 59 mil. € | 3 | 4 | 6,0 | |||||
29 | 7. | 2/2024 | D1 | 4 | 1 235 mil. € | 1 | 1 | 7,0 | |||||
30 | 13. | 8/2024 | R2 | 2 | 169 mil. € | 2 | 2 | 8,0 | |||||
31 | 14. - 15. | 10/2024 | R7 | 2 | 172 mil. € | 4 | 4 | 6,0 | |||||
32 | 42. - 43. | 11/2028 | R3 | 2 | 63 mil. € | 3 | 2 | 3,0 | |||||
33 | 27. | 5/2026 | D3 | 4 | 410 mil. € | 1 | 1 | 7,0 | |||||
33 úsekov |
2 - 8 |
6 515 mil. € |
2,6 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku