dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
276,0 km |
2 - 6 |
5 742 mil. € |
3,8 |
3,5 |
32 - 62 |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 8/2007 | 7/2024 | 32 | |||
2 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 3 | 3 | 10/2009 | 3/2024 | 37 | |||
3 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 12/2007 | 7/2020 | 38 | |||
4 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 3 | 2 | 11/2008 | 11/2011 | 39 | |||
5 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 12/1998 | 7/2011 | 40 | |||
6 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 12/1998 | 11/2010 | 41 | |||
7 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 4 | 3 | 12/2011 | 2/2023 | 42 | |||
8 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 7/2010 | 4/2023 | 44 | |||
9 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 1/2007 | 5/2026 | 45 | |||
10 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 3 | 3 | 2/2009 | 6/2024 | 46 | |||
11 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 5/2008 | 9/2023 | 47 | |||
12 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 5 | 5 | 12/2007 | 11/2023 | 48 | |||
13 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 5/2008 | 1/2025 | 49 | |||
14 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | 7/2004 | 7/2024 | 51 | |||
15 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 | 3 | 7/2004 | 7/2024 | 50 | |||
16 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 4 | 3 | 7/2004 | 7/2024 | 52 | |||
17 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | 4/2005 | 3/2025 | 53 | |||
18 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | 4/2005 | 3/2025 | 54 | |||
19 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 9/2009 | 11/2026 | 56 | |||
20 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 9/2009 | 11/2026 | 55 | |||
21 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 5/2008 | 3/2027 | 57 | |||
22 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 5/2006 | 2/2026 | 58 | |||
23 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 4 | 2 | 5/2007 | 3/2026 | 59 | |||
24 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 3 | 2 | 5/2007 | 3/2026 | 60 | |||
25 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 11/2009 | 3/2027 | 62 | |||
26 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 11/2009 | 3/2027 | 61 | |||
276,0 km |
2 - 6 |
5 742 mil. € |
3,8 |
3,5 |
32 - 62 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku