dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 1 550 - 2 151 | 2 | 3 | 11/2010 | 8/2022 | 4/2023 | ||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 3 529 - 4 138 | 2 | 4 | 9/2006 | 2/2025 | 1/2026 | ||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 4 830 | 1 | 2 | 7/2011 | 2/2025 | 11/2026 | ||||
4 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 3 900 - 4 025 | 1 | 3 | 2/2015 | 5/2021 | 9/2022 | ||||
5 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 4 171 - 5 126 | 1 | 1 | 2007 | 4/2025 | 5/2026 | ||||
6 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 5 304 | 1 416 | 2 | 2 | 6/2008 | 4/2022 | 3/2024 | ||||
7 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 5 792 - 7 064 | 1 175 - 1 286 | 3 | 2 | 6/2013 | 7/2023 | 12/2024 | ||||
8 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 5 277 - 6 250 | 1 466 - 1 525 | 2 | 2 | 10/2008 | 8/2022 | 8/2024 | ||||
72,9 km |
2 - 4 |
1 917 mil. € |
5 277 - 30 731 | 1,8 |
2,4 |
9/2022 - 11/2026 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku