dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | Šalková | 173 mil. € | 1 550 - 2 151 | 2 | 3 | 61. | |||
2 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 1 416 | 2 | 2 | 74. | ||||
3 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | Krásno nad Kysucou | 309 mil. € | 3 529 - 4 138 | 2 | 4 | 8. | |||
4 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 4 830 | 1 | 2 | 4. | ||||
5 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | Kapušany | 299 mil. € | 3 900 - 4 025 | 1 | 3 | ||||
6 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 1 175 - 1 286 | 3 | 2 | 56. | |||
7 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | Zacharovce, Bátka | 169 mil. € | 1 466 - 1 525 | 2 | 2 | 86. | |||
8 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | Brodno, Kysucké Nové Mesto | 410 mil. € | 4 171 - 5 126 | 1 | 1 | 3. | |||
72,9 km |
2 - 4 |
1 917 mil. € |
1,8 |
2,4 |
3. - 86. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku