dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
533,1 km |
2 - 8 |
10 055 mil. € |
2,9 |
3,0 |
3. - 49. | ||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | Šalková | 173 mil. € | 5 036 | 2 | 3 | 27. | |||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 3 | 2 | 6. | ||||
3 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | Ivanka sever | 149 mil. € | 11 991 | 1 | 1 | ||||
4 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | Senec | 234 mil. € | 10 827 | 2 | 1 | ||||
5 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | ||||||
6 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 2 002 | 2 | 2 | 34. | ||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | Dlhá nad Oravou | 77 mil. € | 1 390 | 2 | 2 | 16. | |||
8 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | Zemné | 227 mil. € | 1 508 | 4 | 4 | 22. | |||
9 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 116 mil. € | 1 396 | 2 | 3 | 14. | |||
10 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 2 292 | 5 | 5 | 42. | ||||
11 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 3 150 | 4 | 5 | 35. | |||
12 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | Hubová, Likavka, Ivachnová | 341 mil. € | 4 597 | 1 | 1 | |||||
13 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | Čierna voda, Rača | 1 | 2 | |||||||
14 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | Jablonov n.Turňou | 73 mil. € | 1 992 | 5 | 4 | 49. | |||
15 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 1 | 2 | |||||||
16 | 1. | 10/2021 | R4 | 14,3 km | 4 | R 24,5/100 | Košice-juh, Krásna, Hrašovík | 202 mil. € | 3 530 | 2 | 1 | ||||
17 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | Ludvíkov Dvor, Haniska | 171 mil. € | 1 700 - 4 420 | 3 | 3 | ||||
18 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | Kriváň | 267 mil. € | 1 840 | 3 | 4 | |||||
19 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | Trenčín juh, Trenčianska Turná | 143 mil. € | 5 360 | 3 | 4 | 48. | |||
20 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | privádzač Krupina | 70 mil. € | 1 489 | 2 | 2 | 47. | |||
21 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 133 mil. € | 974 | 4 | 3 | 44. | |||
22 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | Svidník sever | 94 mil. € | 2 965 | 3 | 3 | 36. | |||
23 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | Lietavská Lúčka | 555 mil. € | 10 992 | 1 | 2 | |||||
24 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | Lipníky | 105 mil. € | 2 382 | 2 | 2 | 3. | |||
25 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 4 | 4 | 33. | |||||
26 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | Mliečany s II/507, Dolný Bar | 161 mil. € | 2 880 | 4 | 5 | 18. | |||
27 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Moldava nad Bodvou, Šaca | 224 mil. € | 1 604 | 3 | 5 | 41. | |||
28 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Mošovce,
Horná Štubňa | 71 mil. € | 4 | 3 | 7. | ||||
29 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | Mýtna | 142 mil. € | 2 | 2 | ||||||
30 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | Podbiel | 199 mil. € | 1 500 | 2 | 3 | 17. | |||
31 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | Bešeňov, Čaka | 230 mil. € | 5 | 5 | 24. | ||||
32 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | Rimavská Sobota | 125 mil. € | 4 | 4 | 45. | ||||
33 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 1 324 | 2 | 4 | 30. | ||||
34 | 7/2019 | R4 | 4,3 km | 4 | R 24,5/100 | Prešov - sever | 179 mil. € | 5 339 | 1 | 3 | |||||
35 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | Kapušany | 299 mil. € | 4 389 | 1 | 3 | ||||
36 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 3 | 5 | ||||||
37 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 12 mil. € | 908 | 2 | 1 | |||||
38 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Giraltovce | 124 mil. € | 2 113 | 3 | 3 | 21. | |||
39 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 92 mil. € | 4 | 2 | 7. | |||||
40 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Okrúhle | 122 mil. € | 1 908 | 2 | 2 | 15. | |||
41 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 3 | 2 | 25. | ||||
42 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | Ružomberok juh, Ružomberok východ | 155 mil. € | 1 230 | 4 | 3 | 7. | |||
43 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | križovatka D1 | 100 mil. € | 1 544 | 4 | 3 | 7. | |||
44 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | D 26,5/100 | 60 mil. € | 5 | 5 | ||||||
45 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | Slovenská Ľupča, Korytnica | 785 mil. € | 3 | 3 | 7. | ||||
46 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Stročín | 101 mil. € | 1 951 | 4 | 3 | 38. | |||
47 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Plešivec | 176 mil. € | 2 112 | 5 | 5 | 37. | |||
48 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 3 004 | 3 | 4 | 23. | ||||
49 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | Turany 2, Hubová | 1 235 mil. € | 6 458 | 1 | 1 | 4. | |||
50 | 3/2021 | R3 | 4,4 km | 2 | R 24,5/100 v polovičnom profile | Nižná,
Nižná - sever | 70 mil. € | 2 165 | 2 | 2 | |||||
51 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Turňa nad Bodvou | 117 mil. € | 1 747 - 1 961 | 5 | 4 | 31. | |||
52 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | Zacharovce, Bátka | 169 mil. € | 2 147 | 2 | 2 | 40. | |||
53 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | Nové Zámky | 172 mil. € | 965 | 4 | 4 | 22. | |||
54 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | Hunkovce, Vyšný Komárnik | 129 mil. € | 2 660 | 4 | 3 | 46. | |||
533,1 km |
2 - 8 |
10 055 mil. € |
2,9 |
3,0 |
3. - 49. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku