dátum |
plánovaný
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
54 úsekov |
533,1 km |
2 - 8 |
175,8 min. |
2,9 |
3,0 |
12/2013 - po 2040 |
||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 2 | 3 | 9,0 | 4/2023 | |||||
2 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 3 | 2 | 5,0 | 3/2028 | |||||
3 | 3. | 3/2022 | D1 | 3,5 km | 8 | 1 | 1 | 8,0 | 3/2022 | |||||
4 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 2 | 1 | 5,0 | 6/2027 | |||||
5 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 5 | 5 | 4,0 | 2/2029 | |||||
6 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 3,9 min. | 2 | 2 | 8,0 | 3/2024 | ||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 2,7 min. | 2 | 2 | 6,0 | 10/2025 | ||||
8 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 4 | 4 | 5,0 | 10/2024 | |||||
9 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 4,0 min. | 2 | 3 | 5,0 | 6/2027 | ||||
10 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 6,2 min. | 5 | 5 | 4,0 | 9/2029 | ||||
11 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 4,5 min. | 4 | 5 | 6,0 | 3/2024 | ||||
12 | 12/2013 | D1 | 14,9 km | 4 | 7,6 min. | 1 | 1 | 12/2013 | ||||||
13 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 7/2016 | |||||||
14 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 4,9 min. | 5 | 4 | 4,0 | 2/2028 | ||||
15 | 7/2016 | D4 | 22,6 km | 4 - 6 | 1 | 2 | 7/2016 | |||||||
16 | 1. | 10/2021 | R4 | 14,3 km | 4 | 2 | 1 | 10,0 | 10/2021 | |||||
17 | 6. | 7/2023 | R2 | 6,8 km | 4 | 3 | 3 | 9,0 | 7/2023 | |||||
18 | 3/2020 | R2 | 9,1 km | 4 | 4,4 min. | 3 | 4 | 7,0 | 3/2020 | |||||
19 | 24. | 12/2025 | R2 | 6,1 km | 4 | 3,1 min. | 3 | 4 | 7,0 | 12/2025 | ||||
20 | 12. | 7/2024 | R3 | 6,5 km | 2 | 2 | 2 | 6,0 | 7/2024 | |||||
21 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 5,4 min. | 4 | 3 | 4,0 | 5/2030 | ||||
22 | 19. | 6/2025 | R4 | 8,2 km | 2 | 5,2 min. | 3 | 3 | 7,0 | 6/2025 | ||||
23 | 6/2014 | D1 | 13,5 km | 4 | 7,6 min. | 1 | 2 | 6/2014 | ||||||
24 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 1,7 min. | 2 | 2 | 5,0 | 8/2026 | ||||
25 | 26. | 4/2026 | R2 | 20,7 km | 2 | 13,1 min. | 4 | 4 | 5,0 | 4/2026 | ||||
26 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 4 | 5 | 5,0 | 12/2024 | |||||
27 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 11,3 min. | 3 | 5 | 5,0 | 12/2026 | ||||
28 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 4 | 3 | 4,0 | 9/2029 | |||||
29 | 8/2019 | R2 | 13,5 km | 4 | 6,5 min. | 2 | 2 | 9,0 | 8/2019 | |||||
30 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 5,1 min. | 2 | 3 | 6,0 | 10/2025 | ||||
31 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 5 | 5 | 4,0 | po 2040 | |||||
32 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 6,7 min. | 4 | 4 | 5,0 | 8/2026 | ||||
33 | 41. | 9/2028 | R2 | 11,5 km | 2 | 7,3 min. | 2 | 4 | 5,0 | 9/2028 | ||||
34 | 7/2019 | R4 | 4,3 km | 4 | 1 | 3 | 10,0 | 7/2019 | ||||||
35 | 4. | 9/2022 | R4 | 10,2 km | 4 | 1 | 3 | 10,0 | 9/2022 | |||||
36 | 10. | 4/2024 | D1 | 3,8 km | 2 | 3 | 5 | 8,0 | 4/2024 | |||||
37 | 18. | 4/2025 | D1 | 1,1 km | 2 | 2 | 1 | 7,0 | 4/2025 | |||||
38 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 4,4 min. | 3 | 3 | 4,0 | 5/2030 | ||||
39 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 4 | 2 | 4,0 | po 2040 | |||||
40 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 4,4 min. | 2 | 2 | 5,0 | 6/2027 | ||||
41 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 9,4 min. | 3 | 2 | 8,0 | 12/2024 | ||||
42 | 11. | 6/2024 | R1 | 2,7 km | 4 | 4 | 3 | 6,0 | 6/2024 | |||||
43 | 30. | 10/2026 | R1 | 4,6 km | 4 | 4 | 3 | 3,0 | 10/2026 | |||||
44 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 5 | 5 | 5,0 | ||||||
45 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 3 | 3 | 4,0 | 2/2028 | |||||
46 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 3,8 min. | 4 | 3 | 4,0 | 5/2030 | ||||
47 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 11,1 min. | 5 | 5 | 4,0 | 2/2029 | ||||
48 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 1,2 min. | 3 | 4 | 6,0 | 10/2025 | ||||
49 | 7. | 2/2024 | D1 | 13,5 km | 4 | 7,6 min. | 1 | 1 | 7,0 | 2/2024 | ||||
50 | 3/2021 | R3 | 4,4 km | 2 | 3,4 min. | 2 | 2 | 11,0 | 3/2021 | |||||
51 | 47. | 7/2029 | R2 | 14,0 km | 2 | 8,8 min. | 5 | 4 | 4,0 | 7/2029 | ||||
52 | 13. | 8/2024 | R2 | 8,3 km | 2 | 5,2 min. | 2 | 2 | 8,0 | 8/2024 | ||||
53 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 4 | 4 | 6,0 | 10/2024 | |||||
54 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 5,2 min. | 4 | 3 | 4,0 | 11/2028 | ||||
54 úsekov |
533,1 km |
2 - 8 |
175,8 min. |
2,9 |
3,0 |
12/2013 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku